Applicant is required to submit online application to MIDC SWC Portal and written notice as per clause no. 10.2 (f) of DCR 2009 regarding completion of the development in Form No. 8 enclosed in MIDC DCR, 2009, duly signed by the Registered Architect and is submitted to the concerned SPA.
The proposal will be automatically forwarded to concerned Fire Officer for issuance of Final Fire NOC on the same date of online application by Owner. Concerned Fire Officer shall issue Final Fire NOC within 15 days from the date of online application.
The architect/applicant has to submit all mandatory documents along with the as-built plans & upload online.
Joint inspection shall be carried out by Fire department and SPA for High, Risk Buildings within 7 working days from issuance of Fire NOC. Site Inspection report shall be uploaded within 48 hours after inspection.
Site inspection is to be done to determine whether the building is as per the approved plans and is as per norms of MIDC DCR-2009 and if the structure violates the regulations of MIDC, DCR-2009/ found deviation in approved Building Plans then compounding charges shall be levied wherever applicable.
Occupancy certificate will be issued to the applicant subject to condition of payment of all charges and submission of all mandatory documents.