Ease of Doing Business In MIDC

Occupancy Certificates

+
Procedure & Checklist

Applicant is required to submit online application to MIDC SWC Portal and written notice as per cl no. 10.2 (f) of DCR 2009 regarding completion of the development in Form No. 8 enclosed in MIDC DCR, 2009, duly signed by the Registered Architect and is submitted to concerned SPA. Only Online Submission through MIDC SWC is to be done .Plot owners (Applicant) will submit an online Building Permission application. The details furnished will be the plot information (available from LMS), architect details along with the proposed AutoCAD plan (prepared by appointed Architect).

After computerized allocation of site inspector, the concerned person shall carry out site inspection as per the risk based classification. Low Risk and Medium Risk Buildings will be exempted from site inspection.

SPA shall verify the construction as per the approved Building Plans and as per commencement certificate issued.

SPA shall upload the report accordingly on website & recover compounding charges if applicable.

SPA shall verify the required documents for issuing OC and process to issue Occupancy certificate.

Joint Inspection will be carried out by concerned Special Planning Authority, Fire Department, Engineering ,Planning, Water Department, Land Survey, Tree Officer and other internal Department (if required) responsible for granting development /construction permit in MIDC Areas.

+
Timeline

On line Submission and Uploading of Inspection Report on MIDC Website within 48 Hours is Mandatory for all Inspectors

+
Mandate
Back to the Top