Ease of Doing Business In MIDC

Construction Permit

+
Procedure & Checklist

After computerized allocation of site inspector, the concerned person shall carry out site inspection as per the risk based classification. Low Risk and Medium Risk Buildings will be exempted from site inspection.

SPA shall verify the site as per the documents submitted by applicant from concerned Regional Office.

SPA shall upload the report accordingly on BPAMS portal & recover compounding charges if applicable.

SPA shall verify the required documents for Building Plan Approval and process to issue commencement certificate and approval to the Building Plans.

Joint Inspection will be carried out by concerned Special Planning Authority, Fire Department, Engineering ,Planning, Water Department, Land Survey, Tree Officer and other internal Department (if required) responsible for granting development /construction permit in MIDC Areas.

+
Timeline

On line Submission and Uploading of Inspection Report on MIDC Website within 48 Hours is Mandatory for all Inspectors.

+
Mandate